A team member has missed two sprint commitments and has gone quiet in stand-ups. What should the project manager do first?
- Meet the team member privately to understand what is affecting their work
- BReassign their remaining tasks to a stronger team member
- CRaise the missed commitments in the next retrospective in front of the team